Investigate and design gross pollutant trap, prepare final drawing, hydraulic report, dilapidation report, review of environmental factors, DBYD, WHS&E, environmental controls, stormwater diversion, excavation, shoring, Build insitu and precast stormwater pits, excavation of stormwater channel, insitu formwork and concreting, steel fixing, water management, excavate and construct access driveway, carpark works, line marking, site restoration.
Before construction commenced
Excavation and sheet piling and water bypass installed
Precast stormwater pit. Formwork and steel for base slab of GPT
Formwork of first riser of walls
First lid poured, grate installed and steel work to be installed
Formation of second lid with grate block out
Rock work around unit
Multi-level GPT concrete works
Multi-level GPT concrete works
Fence installation and new kerb and gutter
Concrete layback and bollards installed
Line marking of carpark to complete project